Current Projects

Citizens can keep up to date with any special or disruptive construction or maintenance projects that are being managed by the Inkster DPS Department

IMPORTANT 

NEWS ABOUT YOUR NEIGHBORHOOD 

Inkster Logo  Seal_Page_1

 CITY OF INKSTER 

JOHN DALY STREET IMPROVEMENTS 

IMPORTANT PROJECT UPDATE 

Public Notice:

Please read the Public Notice for an overview of the project including the scope of work and planned key target dates.

Due to the COVID-19 Global Pandemic and Executive Order No. 2020-21 issued by Governor Whitmer on March 23, 2020, construction on John Daly Street will be suspended until the “Stay Home, Stay Safe” order is lifted. Construction is currently expected to resume mid-April. 

During this time the John Daly Street will remain closed and the detour will remain in place.

Project Description 

The City of Inkster has allocated funds for the reconstruction of John Daly Street from Michigan Avenue to the Rouge River for an approximate length of one-third of a mile. These funds shall be used for the construction of water main, sanitary and storm sewers, curb/gutter, concrete sidewalks including ADA ramps, material quality control testing, and concrete street reconstruction. 

Phase 1, Rouge River to Inkster Park, was completed in 2019. 

Access 

There will be a few individual residences along John Daly St. that will have their driveways restricted throughout construction. The contractor will work with those particular residents if access to the garage is required. 

Tentative Key Construction Dates – these are project and weather dependent 

Phase 2 – Start February 17, 2020 – complete July 31, 2020 

Phase 2 Michigan Avenue to Inkster Park 

John Daly St. will be completely closed from Michigan Avenue to Inkster Park for all remaining reconstruction work completion. During this phase, residents will be able to access Inkster Park from the north. 

Project Detours 

A detour route will be posted. 

Public Services 

  • Trash Collection – Trash collection will be unaffected by the construction 
  • Mail Service – Mail service will be uninterrupted by construction 

Frequently Asked Questions 

  • How will access to homes be maintained? 

In order to expedite construction, John Daly will be completely closed for Phase 2. If residences require access to garages on John Daly St residents are encouraged to contact the Project Engineer to coordinate with the contractor for access. 

  • Will trees be removed as part of the construction project? 

Some trees are scheduled to be removed as part of the construction project and will only be removed as necessary. Trees scheduled for removal will not be replaced. 

  • What about lawn restoration? 

Disturbed lawn areas will be fully restored to pre-construction conditions with topsoil, fertilizer, seed, and mulch. If necessary, the contractor will return in the fall of 2020 to ensure grass growth. 

If you have any specific questions regarding road construction, please contact: 

Daniel Guastella 

Project Engineer 

Benesch 

(313) 400-3707 

dcguastella@benesch.com 

For General Questions please contact the Project Engineer between 9:00 AM and 4:00 PM. 

We appreciate your patience, during construction!